Bulk Material Handling Systems
Bulk Material Handling Systems
List of Operation & Maintenance Jobs (Ongoing & Completed by the Group)
Complete Thermal Power Station
-
S. NO.
Name of Project
Unit Capacity
Status
-
1.
Coal fired Thermal Power Station at Butibori, Nagpur of Indo Rama Synthetics Ltd.
2x15 MW + 1x11 MW
Ongoing since 2006
-
2.
Coal fired Thermal Power Station at Dibba, UAE of Fujairah Cement Industries
2x20 MW + 1x12 MW
Ongoing since 2010
-
3.
Coal Fired HTM Plant at Butibori, Nagpur of Indorama Synthetics Ltd.
2x13.0 & 14.2 M kcal/hr.
Ongoing since 2011
-
4.
DG Power Plant at Butibori, Nagpur of Indorama Synthetics Ltd.
44.5 MW (3x13.5 MW + 1x4 MW DG Sets)
Ongoing since 2013
-
5.
Coal / Lignite fired Power Station at Dalmiapuram of Dalmia Cement Ltd.
1x29 MW + 1x19 MW
Duration – 9 Years (2005 to 2014)
-
6.
Coal Fired Power Station at Jharsuguda, Odisha of Action Ispat & Power Pvt. Ltd.
2x43 MW
Duration – 8 Months (Jan. to Sep. 2014)
-
7.
Oil fired Power Plant and 4x10000 Cum / day Desalination Plant at Homs Power Station Libya. The services included, besides the O&M activities, training of Libyan Engineers and Technicians & pre commissioning activities.
4x120 MW
Duration - 4 Years (1980 to 1984)
-
8.
Baggase based Co-generation Power Station at Sameerwadi, Karnataka of Godavari Biorefineries Ltd.
1x24 MW + 1x21.56 MW
Duration - 11 Years (2002 to 2013)
-
9.
Bagasse based Co-generation Power Station of Dalmia Chini Limited, Sitapur
1x24 MW
Duration - 1 Year
-
10.
Coal / Washery Rejects fired Power Station at Durgapur (Mangalpur)
1x19 MW
Duration - 4 Years
-
11.
Coal / Washery Rejects fired Power Station at Ramrupai, Durgapur of Jaibalaji Industries Ltd.
2x25MW
Duration -1 Year
Ash Handling Systems
-
S. NO.
Name of Project
Unit Capacity
Status
-
1.
Mundra Ultra Mega Power Station of Tatas
5x800 MW
Ongoing since 2015
-
2.
Thermal Power Station at Tiroda of Adani
5x660 MW
Ongoing since April, 2016
-
3.
Wanakbori Thermal Power Station
7x210 MW
Ongoing since 1984
-
4.
Raichur Thermal Power Station of Karnataka Power Corporation Ltd.
4x210 MW
Ongoing since 1988
-
5.
Parichha Thermal Power Station of Uttar Pradesh Rajya Vidyut Utpadan Nigam Ltd.
2x110 MW + 2x210 MW
Ongoing since 1992
-
6.
Durgapur Thermal Power Station Units # 3 to 6 of Durgapur Projects Ltd.
410 MW
2007 - 2014
-
7.
Bandal Thermal Power Station of West Bengal Power Development Corporation Ltd.
1x210 MW
1989-2010 ????
-
8.
Panipat Thermal Power Station Units # 1 & 2 of Haryana Power Generation Corporation Ltd.
2x110MW
Ongoing since 2005
-
9.
Thermal Power Station at Lapanga, Odisha of Hindalco
4x150 MW
Ongoing since 2015
-
10.
Durgapur Thermal Power Station of Durgapur Projects Limited
551 MW
Ongoing since 2014
-
11.
Chandrapura Thermal Power Station
3x130 MW
Duration – 24 Years (1991 to 2015)
-
12.
Andal Thermal Power Station of Damodar Valley Corporation
2x500 MW
Duration – 5 Years (2011 to 2016)
-
13.
Bellary Thermal Power Station of Karnataka Power Corporation Ltd.
1x500 MW
Duration – 5 Years (2011 to 2016)
-
14.
Hissar Thermal Power Station of Haryana Power Generation Corporation Ltd.
2x600 MW
Duration – 3 Years (2012 to 2015)
-
15.
Yamunanagar Thermal Power Station of Haryana Power Generation Corporation Ltd.
2x300 MW
Duration – 1 Year (2014 to 2015)
-
16.
Raghunathpur Thermal Power Station of Damodar Valley Corporation
1x600 MW
Duration – 6 Months